Old River Nene Closure at March Town Bridge

Notice – Suspension of Navigation

Middle Level Acts 2018 – Section 7
NOTICE IS HEREBY GIVEN THAT: closure of navigation of or through the below mentioned
waterway forming part of the Middle Level System will be between –

4th November 2024 – 27th January 2025

TOWN BRIDGE, OLD RIVER NENE, MARCH

This is for the purpose of undertaking remedial works which include, vegetation removal from the
structure and cleaning, brickwork repointing, replacement of deteriorated brickwork, localised
reinforced concrete repairs, strengthening of bridge structure and supports, and bridge repainting.
Other parts of the Middle Level Navigations, not the subject of the closure during these periods, will
remain open. Diversion route is via the Twenty Foot River (subject to bridge height) or via the Forty
Foot and Sixteen foot waterways.

Should the above works be completed before 27th January 2025, Town Bridge navigation will be re-
opened.

Dated this day – 1st October 2024

P BURROWS
Chief Executive
Middle Level Offices